EDS NMCI


Austin Commercial served as construction manager for EDS on a $95 million program, which involves the installation of data and telecommunication servers at more than 65 military bases throughout the United States and Japan. The scope of work included: mechanical, electrical, plumbing services, civil, structural, architectural services, racking, backbone fiber, security and commissioning.

The EDS NMCI project was on a tight, fast-track schedule. Notice to proceed was given April 1, 2003 with design beginning May 15, 2003 and procurement June 15, 2003. Construction on several projects began August 15 with a completion date of September 15. Other projects began August 15 and were completed November 15, 2003.

Austin moved quickly from one site to another upon completion of each project. Austin Commercial completed work on 50 sites in three months, with several projects under construction at the same time.