Dallas North Tollway-501


This time-sensitive project included the construction of two bridges for future main lanes, while maintaining traffic at grade. The project also included the construction of new frontage roads within job limits. Drill shaft retaining walls with a pre-cast fascia, lime-treated subgrade, and concrete curbed roadway completed the project. The major milestone, eight months into the project was met to allow the opening of the Firewheel Mall. Project was completed on time.

Company

Austin Bridge & Road

Category

Toll Turnpike